Project Stats
From Aerials

Project Statistics:

  • Hospital Square Footage: 440,887
  • Shelled space: 50,000 SF
  • Site Size: 26.5 acres
  • Hospital Beds: 241 (311 once shelled space is built out)
  • Average # of construction workers per day: 308
  • # of Accelerometers on building and site that relay to CSMIP satelites after an earthquake: 5
  • Amount of concrete used on the project: approximately 60,000,000lbs or 1,500 truckloads
  • Lineal feet of copper wire installed on the project: 6,500,000 LF (250,000lbs)
  • Structural System: Steel Braced Frame, base isolated
  • Earthquake magnitude hospital could withstand and remain fully operational: 8.0
  • Maximum horizontal displacement during an earthquake: 30″
  • Maximum vertical displacement during and earthquake: 2″
  • Percent of total project cost spent on seismic assemblies: 5%
  • Length of 60″ Hetch-Hetchy waterline that had to be re-routed during the project: 600 LF
  • Operating Rooms: 10 (one shelled for future build-out)
  • MRIs: 2 (3T & 1.5T)
  • CT Scanners: 2
  • Nuke Med Machines: 2
  • Projected ER visits per year: 50,000
  • Specialty Procedure Suites: Stereotaxis, IR, Cath Lab, Endoscopy
  • 3D Modeling Software Used in coordination:  Navisworks
  • Number of seismic portals between the isolated hospital and the fixed base POB: 6
  • Types of seismic moat covers: 4
  • Type of base isolators: Friction pendulum
  • Number of base isolators: 176
  • Number of linear viscous dampeners: 32
  • Distance from San Andreas Fault: 1.67 Miles
  • Number of different exterior wall systems: 5
  • Number of fountains: 2
  • Number of courtyards: 5
  • Project Phases: 5
  • Volume of recycled air: 0 CFM
  • Number of emergency generators: 3
  • Number of electrical systems: 17
  • Number of Hospital Staff: 2000+
  • Number of Fire Smoke Dampeners: 965
  • Max number of construction personnel on site in one day: 500+
  • Average floor height: 17 feet
  • Planning Began: 1994
  • Groundbreaking: 11-1-2006
  • Substantial Completion: 2-16-2011
  • Patient Move In Date: 5-15-2011
  • Number of OSHPD back-checks during permitting: 5
  • Total Program Budget: $643,000,000
  • Amount of tax-payer funding: $0
  • Lean Construction Methods used: shared incentives, Design assist trade partners, 3D Model coordination, Reverse phase schedules, location based scheduling, 10 week look- ahead schedules, weekly work plans (WWP), Percent Plan Complete (PPC), Project Constraint Log, Value Stream Mapping of Commissioning process.
  • Volume of work performed on time and materials:  approx $250M
  • Air Filtration Rate: 95%
  • # of Parking structure stalls: 800
  • Average # of inspections per week: 300
  • Total inspections: approximately 14,000
  • Medsurge/Acute care beds: 175 private beds
  • Critical Care: 24 private beds
  • Family Birthing Center beds: 30 private beds
  • Neonatal Intensive Care: 6 private beds (licensed for 12 semi-private beds)
  • Diagnostic Imaging Suites
  • Cardiac Catheterization and Angiography suites
  • Preoperative Services- (surgery, Endoscopy, Bronchoscopy, Short Stay, Pre-Op testing)
  • Cardiology and Neurology Services
  • Cardiac Rehabilitation
  • Physical Therapy, Occupational Therapy & Speech Therapy
  • Dialysis
  • Pharmacy
  • Support Services (Materials Management, Central Processing, Information Services, Housekeeping, Engineering)
  • Central Utility Plant